FY2024 Military Construction Appropriations: A Summary

FY2024 Military Construction Appropriations: A Summary
Updated April 25, 2024 (IN12238)

On March 9, 2023, the Biden Administration submitted the FY2024 President's Budget Request (PBR) seeking $16.675 billion for U.S. Department of Defense (DOD) military construction (MILCON) and family housing programs. The request was $2.325 billion (12%) less than the $19.000 billion provided for such programs in the Military Construction, Veterans Affairs and Related Agencies Appropriations Act, 2023 (Division J of P.L. 117-328). The House-passed version of the legislation for FY2024 (H.R. 4366) proposed appropriating $799 million (4.8%) more than the requested amount. The Senate Appropriations Committee-reported version of the legislation (S. 2127) recommended $2.395 billion (14.4%) more than the requested amount. On March 9, 2024, President Biden signed P.L. 118-42, which provided $18.675 billion for the FY2024 MILCON and family housing programs, 12% above the requested amount (Table 1). Explanatory materials and bill funding tables for Division A, the Military Construction, Veterans Affairs and Related Agencies Appropriations (MILCON-VA) Act are contained in the March 5, 2024 Congressional Record.

A list of selected projects funded in the legislation is included in Table 2.

The FY2024 MILCON-VA appropriations act included 11 projects that were incrementally funded (i.e., Congress provided a portion of the requested amount for a particular project). By incrementally funding certain projects, Congress allows DOD to initiate the construction project but DOD will likely have to request additional funding in a future budget cycle to complete the project. In July 2023, the Biden Administration cited opposition to the House-passed version of the MILCON-VA bill because it proposed funding 24 projects incrementally.

The act appropriated funding for 143 MILCON projects that were not included in the President's budget request but were listed as Community Project Funding or Congressionally Directed Spending items. Appropriations for those projects totaled about $1.565 billion.

Table 1. Military Construction Appropriation Legislation for FY2024

(in thousands of dollars of budget authority)

Account

FY2023 Enacted

FY2024 Request

H.R. 4366

S. 2127

FY2024 Enacted

Military Construction, Army

$1,553,825

$1,470,555

$1,517,455

$1,876,875

$2,022,775

Military Construction, Navy & Marine

$4,345,320

$6,022,187

$4,477,961

$6,046,309

$5,531,369

Military Construction, Air Force

$2,614,996

$2,605,314

$2,439,614

$2,802,942

$2,741,424

Military Construction, Defense-wide

$2,626,078

$2,984,682

$2,651,047

$3,132,782

$3,161,782

Military Construction, Army National Guard

$459,018

$340,186

$369,261

$598,572

$620,647

Military Construction, Army Reserve

$193,878

$107,076

$117,076

$151,076

$151,076

Military Construction, Navy & Marine Reserve

$36,837

$51,291

$61,291

$51,291

$51,291

Military Construction, Air National Guard

$279,353

$178,722

$189,322

$304,426

$295,526

Military Construction, Air Force Reserve

$85,423

$291,572

$330,572

$309,572

$331,572

NATO Security Investment Program

$220,139

$293,434

$293,434

$293,434

$293,434

Base Realignment and Closure

$574,687

$389,174

$539,174

$439,174

$489,174

Subtotal, Military Construction

$12,989,554

$14,734,193

$12,986,207

$16,006,435

$15,690,070

Subtotal, Family Housing

$1,986,330

$1,940,751

$1,970,751

$1,940,751

$1,970,751

Subtotal, Administrative Provisions

$4,024,116

$0

$2,517,042

$1,122,814

$1,014,179

Total, Military Construction

$19,000,000

$16,674,944

$17,474,000

$19,070,000

$18,675,000

Sources: H.Rept. 118-122, pp. 96-100; S.Rept. 118-43, pp. 106-109, P.L. 118-42.

Note: Family Housing budget numbers include Family Housing Construction, the Family Housing Operation & Maintenance, Family Housing Improvement Fund (FHIF), and the Unaccompanied Housing Improvement Fund (UHIF).

Selected Funding Items

In Section 124, the appropriations act provided $514.1 million for additional construction funds for projects listed on DOD's FY2024 unfunded priorities lists.

The appropriations included $662.4 million for planning and design and construction of new barracks facilities, also known as unaccompanied housing. That includes Section 132, in which Congress appropriated $15 million for each of the three military departments for planning and design for new barracks facilities. The joint explanatory statement that accompanied the enacted law directs each of the services to provide the defense committees with a report for how the services intend to address poor condition of barracks facilities that the Government Accountability Office (GAO) identified in a report released in September 2023 (GAO–23–105797).

The appropriations included $336.3 million to support Child Development Centers (CDCs), which provided $276.8 million for construction of six new CDCs and $59.5 million in planning and design funding to help develop future construction.

The appropriations act included $69 million for planning and design and $62 million in unspecified minor construction for projects as identified on INDOPACOM's unfunded priorities list.

Table 2. Selected Military Construction Projects Funded by P.L. 118-42

(in thousands of dollars of budget authority)

Location

Project Title

Requested Amount

P.L. 118-42

Joint Base Pearl Harbor-Hickam, HI

Dry Dock 3 Replacement (Inc)

$1,318,711

$1,318,711

Portsmouth Naval Shipyard, ME

Multi-Mission Drydock #1 Extension (Inc)

$544,808

$544,808

Fort Meade, MD

NSAW Recap Building 4 (Inc)

$315,000

$315,000

Joint Region Marianas, GU

PDI: Joint Communication Upgrade (Inc)

$292,830

$146,415

Naval Weapons Station Yorktown, VA

Weapons Magazines

$221,920

$110, 960

Naval Submarine Base New London, CT

Weapons Magazine & Ordnance Operations Facility

$219,200

$109,600

March Air Reserve Base, CA

KC-46 Two Bay Maintenance/Fuel Hangar

$201,000

$201,000

Naval Base Kitsap, WA

Shipyard Electrical Backbone

$195,000

$195,000

Fort Meade, MD

Cybersecurity Operations Facility

$186,480

$186,480

Fort Belvoir, VA

DIA Headquarters Annex

$185,000

$185,000

Guam/Joint Region Marianas, GU

Missile Integration Test Facility

$174,540

$87,270

Ellsworth Air Force Base, SD

B-21 Phase Hanger

$160,000

$160,000

Marine Barracks Washington, DC

Bachelor Enlisted Quarters

$131,800

$65,900

Naval Station Norfolk, VA

MQ-25 Aircraft Laydown Facilities

$114,495

$57,248

Port Hueneme, CA

Laboratory Compound Facilities Improvement

$110,000

$110,000

Port Hueneme, CA

Laboratory Compound Facilities Improvement

$110,000

$110,000

Marine Corps Base, HI

Water Reclamation Facility Upgrade

$0

$109,000

Fort Jackson, SC

Reception Barracks Complex, Phase 2, Cost to Complete

$0

$101,000

Joint Base Pearl Harbor-Hickam, HI

Dry Dock Replacement

$0

$90,000

Lexington Armory, NY

National Guard Readiness Center addition/alteration

$0

$90,000

Joint Base Pearl Harbor-Hickam, HI

Waterfront Production Facility (planning and design)

$0

$49,080

Fort Novosel, AL

Adv. Individual Training Barracks Complex (Cost to Complete)

$0

$41,200

Fort Hunter Liggett, CA

Network Enterprise Center

$0

$40,000

Source: FY2024 Enacted from P.L. 118-47 and Senate, Congressional Record, Daily Edition, Vol. 170, no. 39, part II (March 5, 2024), p. S1246-S1263.

Notes: Projects listed in this table were selected based on a CRS longitudinal analysis of the president's budget request for FY2024, and the House- and Senate-passed drafts of the FY2024 MILCON-VA bills and P.L. 118-47. In a previous CRS Insight about the House- and Senate-passed drafts of the FY2024 MILCON-VA bills, CRS compiled three lists of projects: (1) the 10 largest MILCON projects (by dollar value) that were included in the PBR; (2) the 10 MILCON projects in the House-passed bill that showed the largest proposed change in funding (by dollar value) compared to the president's budget request; and (3) the 10 MILCON projects in the Senate-passed bill that showed the largest proposed change in funding (by dollar value) compared to the president's budget request. The table above includes all of the projects that CRS identified in that analysis of the president's budget request, and the House- and Senate-passed drafts of the FY2024 MILCON-VA bills. Acronyms include NSAW, National Security Agency Washington; PDI, Pacific Deterrence Initiative; and DIA, Defense Intelligence Agency.